INDUSTRY ASSOCIATIONS

Powertx foster strong and lasting relationship with other construction industry leaders and OEM suppliers which can bring synergies and economies producing a broader scale of capabilities and resources and capturing all installation & commissioning requirements including MDR’s and critical spares

  • MV & HV Primary & Secondary Switchgear Providers
  • MV & HV Primary & Secondary Power Transformers Providers
  • Switchroom Providers
  • Civil Contractors
  • Overhead Powerline Contractors
  • National Electrical and Communications Association

COMPLETE SUBSTATION

WORKS: Design, Construct & Project Management of a 66/11kV 25 MVA Substation & associated mine site HV reticulation for the VSA2 Vent Fan & Underground Power Project.

SITE: Kestrel South Mine
CLIENT: Persal & Co For Kestrel Coal

SUBSTATION

WORKS: Construction, Project Management and Commissioning of the 33/132kV 100MVA substation.

SITE: Rugby Run Solar Farm
CLIENT: Adani Renewables

LONGWALL EXTENSION SUBSTATION

WORKS: Design, Construct & Project Management of a 66/11kV 20 MVA Substation for the Longwall Extension feeder.

SITE: Grasstree Underground Mine
CLIENT: Persal & Co For Anglo/Capcoal

SUBSTATION & SWITCHING STATIONS

WORKS: Augmentation of the 66kV Boundary Substation to include 2 x 66kV Switching Stations.

SITE: German Creek Open Cut Mine
CLIENT: Persal & Co For Anglo/Capcoal

SUBSTATION

WORKS: Design, Construct & Project Management of a Temp 66/11kV 8/10 MVA Substation.

SITE: Grasstree Underground Mine
CLIENT: Persal & Co For Anglo/Capcoal

TEMPORARY SUBSTATION

WORKS: Construction of a 132kV to 11kV 15MVA Temporary Substation.

SITE: Eagle Downs JV Mine Construction
CLIENT: Persal & Co For Ampcontrol

CABLE INSTALLATION

WORKS: HV Underground Cable installation, termination and testing site wide.

SITE: BMA Caval Ridge Mine Construction
CLIENT: Persal & Co for Bechtel (Duration: April 2013 – May 2014.)

MAIN SUBSTATION

WORKS: Installation of 10/12.5MVA 66/11kV Main Substation & PFC Unit & Associated mine site HV reticulation.

SITE: Byerwen Mine
CLIENT: Q Coal

DAM SUBSTATION

WORKS: Upgrade/Replacement of Substation and installation of an additional pump at the Worked Water Dam.

SITE: Coppabella Mine
CLIENT: Peabody Energy

11kV RMU REPAIRS

WORKS: Replace SF6 Switching Mechanisms.

SITE: Surat Basin Gas Fields
CLIENT: ABB Australia

SUBSTATION

WORKS: Construction of a 66 kV Switching Substation.

SITE: Saraji Mine BMA
CLIENT: Persal & Co

SWITCHING/METERING STATION

WORKS: Construction of 66kV Switching/Metering Station including incoming and outgoing 66kV landing structures.

SITE: Byerwen mine
CLIENT: Q Coal

DOWNLOAD OUR CAPABILITY STATEMENT

OUR CLIENTS

LEADERS IN THE CONSTRUCTION OF ELECTRICAL INFRASTRUCTURE & HIGH VOLTAGE SERVICES

DESIGNED BY REDHOTBLUE

Power TX